Sealing and Wheeling

We had some sealing going on today. And a bit of "wheeling" if you will.

On the Canadian 337, Chuck sealed around the fasteners that secure the instrument panel access panels in place.

On the Brazilian 206, Paul was placing seal material around a newly installed fuel strainer inside the wing's fuel tank.
Paul "goops up" with sealant.

Paul applies sealant to the rear, inboard corner of the fuel tank.

The "wheeling" was going on over at the Honduran 206 where Andy & Jim aligned the main landing gear for use under fueled and loaded conditions.

Andy reviews the technical data as Jim aligns the left main gear of the Honduran 206.